Timelines

Year One Activities:  2005-2006

 

October-November

  • Convene first quarterly meeting of Region V Consortium to initiate Project Gateway
  • Assignment of Administrative School Improvement Consultant (JBHM Education Group, LLC)
  • Conduct NSDC’s Professional Development online survey
  • Create Region V Project Gateway Web page
  • Conduct pre assessments listed in the evaluation section of this proposal at each school
  • Identify though an interview and hiring process Instructional Coaches
  • Secure contracted services -(JBHM Education Group, LLC)
  • Select a Leadership Team to serve as key leaders in the dissemination of best practices and Focused Study Groups (including one special education teacher)
  • Facilitate sub-group analysis of 2005 data
  • Categorize and prioritize student needs
  • Develop Project Gateway Action Plan and set weekly improvement goals
  • Focused Study Groups- twice a month
  • Assign team members and/or Instructional Coach to SBLC committee meetings
  • Develop strategies to increase positive home-school relations
  • Weekly Progress Reports

December-January

  • Project Gateway quarterly meeting to evaluate progress of activities and submit required SDE reports
  • Reports to Region V Consortium and superintendents on the progress of each school by the contracted services provided by -(JBHM Education Group, LLC)
  • Focused Study Groups- twice a month
  • Weekly Progress Reports

February

  • Conduct mid-year assessments
  • Focused Study Groups- twice a month
  • Weekly Progress Reports

March

  • Reports to Region V Consortium and superintendents on the progress of each school by the contracted services provided by -(JBHM Education Group, LLC)
  • Weekly Progress Reports
  • State assessment

April -May

  • Focused Study Groups- twice a month
  • Conduct post assessments listed in evaluation section of this proposal
  • Develop school based action plans and continue focus for 2005-2006 of Project Gateway
  • Conduct third quarterly meeting to review school based action plans and submit required SDE reports
  • Weekly Progress Reports

July

  • Conduct fourth quarterly meeting to formulate Region V Consortium continued funding plan and submit required SDE reports